A standard machine ships 7–10 days after the drawing is approved; a custom machine takes about 20. The clock starts at drawing approval, not at the enquiry — and the enquiry-to-drawing exchange, not the build, is usually what moves the ship date.
At a glanceClock start Lead time is counted from the approved drawing, not from the enquiry. Until the drawing is signed off, the build has not started. · Standard machines 7–10 days. The platform is a series we already build, so frame, motion and program are adapted rather than designed.
Most engineers arriving here go straight to one of these:
Most buyers read a lead time as production time. It is not. The figures below are counted from an approved drawing, because that is the first moment the machine is fully defined: screw positions, fixture geometry, torque window and cycle-time target are all fixed on that drawing. Before it is approved the build cannot start, and that exchange — not the assembly — is where dates usually slip.
Inside the 7–10 days a standard machine goes through five stages: material and standard parts are picked against the approved drawing; the frame and motion platform are assembled and squared; the feeder and fixture are made to the drawing and loaded with your screws; the program is written for your screw positions and torque window; and the finished machine runs your parts before it is packed. The platform is a series we already build, which is why the window is measured in days rather than weeks.
A custom machine takes about 20 days because three of those five stages start from zero. The fixture is designed rather than adapted, the feed arrangement has to be proven with your actual screws — head form, shank length and coating all change how a screw presents — and the program is written against points that did not exist before. If the feed needs a second trial, that trial is the single most common reason a custom date moves.
Published lead times vary more than most buyers expect. On supplier pages checked in November 2026 we found 7–15 days for standard machines at one supplier, 20–30 days for its custom machines, 15 days (30 in peak season) at a second, 10 working days from deposit at a third, and 20–35 days at a fourth. One manufacturer even quoted 7–15 days on one page and 20–35 days on another, so the number on its own is not comparable. What matters is the starting event and whether the fixture is new.
Four things compress the window, and all four sit with the buyer: send the drawing and the 3D file in one go rather than in three revisions; send physical screws, not just a thread callout, because a burr or a mixed box will stop a feeder during the trial run; state the torque window and the target cycle time as numbers; and settle the data format for traceability before the build, because that is a configuration, not a later rebuild.
What stretches it is rarely the machine. Fixture revisions after the first part is tried, screws that do not match the drawing, a traceability scope added after the program is written, and queue position in a busy month. Ask for the date in writing against an approved drawing, and ask what happens to it if the fixture needs a second iteration.

Last updated 2026-11-20. Screw range, torque and cycle-time figures reflect the current published platform specifications.
The practical conclusions from the sections above.
Lead time is counted from the approved drawing, not from the enquiry. Until the drawing is signed off, the build has not started.
7–10 days. The platform is a series we already build, so frame, motion and program are adapted rather than designed.
About 20 days. Fixture designed from scratch, feed proven with your screws, program written for new points.
Standard machines quoted at 7–15 days, 10 working days, 15 days (30 in peak season) and 20–35 days by four different suppliers.
One complete drawing, physical screw samples, numeric torque and cycle-time targets, traceability format agreed before the build.
Production time ends at packing. Transit depends on destination and mode and is quoted as its own line.
A fastening cycle on the same platform series, filmed on the assembly floor in Dongguan — the fastest way to check the motion, the feed and the torque behaviour before you ask for a drawing.
Describe the part and the joint and we will tell you which configuration fits — or whether you do not need a machine at all.