What the 7–10 day lead time actually covers

A standard machine ships 7–10 days after the drawing is approved; a custom machine takes about 20. The clock starts at drawing approval, not at the enquiry — and the enquiry-to-drawing exchange, not the build, is usually what moves the ship date.

At a glanceClock start Lead time is counted from the approved drawing, not from the enquiry. Until the drawing is signed off, the build has not started. · Standard machines 7–10 days. The platform is a series we already build, so frame, motion and program are adapted rather than designed.

Most engineers arriving here go straight to one of these:

Technical guide

Most buyers read a lead time as production time. It is not. The figures below are counted from an approved drawing, because that is the first moment the machine is fully defined: screw positions, fixture geometry, torque window and cycle-time target are all fixed on that drawing. Before it is approved the build cannot start, and that exchange — not the assembly — is where dates usually slip.

Inside the 7–10 days a standard machine goes through five stages: material and standard parts are picked against the approved drawing; the frame and motion platform are assembled and squared; the feeder and fixture are made to the drawing and loaded with your screws; the program is written for your screw positions and torque window; and the finished machine runs your parts before it is packed. The platform is a series we already build, which is why the window is measured in days rather than weeks.

A custom machine takes about 20 days because three of those five stages start from zero. The fixture is designed rather than adapted, the feed arrangement has to be proven with your actual screws — head form, shank length and coating all change how a screw presents — and the program is written against points that did not exist before. If the feed needs a second trial, that trial is the single most common reason a custom date moves.

Published lead times vary more than most buyers expect. On supplier pages checked in November 2026 we found 7–15 days for standard machines at one supplier, 20–30 days for its custom machines, 15 days (30 in peak season) at a second, 10 working days from deposit at a third, and 20–35 days at a fourth. One manufacturer even quoted 7–15 days on one page and 20–35 days on another, so the number on its own is not comparable. What matters is the starting event and whether the fixture is new.

Four things compress the window, and all four sit with the buyer: send the drawing and the 3D file in one go rather than in three revisions; send physical screws, not just a thread callout, because a burr or a mixed box will stop a feeder during the trial run; state the torque window and the target cycle time as numbers; and settle the data format for traceability before the build, because that is a configuration, not a later rebuild.

What stretches it is rarely the machine. Fixture revisions after the first part is tried, screws that do not match the drawing, a traceability scope added after the program is written, and queue position in a busy month. Ask for the date in writing against an approved drawing, and ask what happens to it if the fixture needs a second iteration.

Overseas buyers walking through the assembly floor in Dongguan with a CBZIN engineer, past working screw driving stations.
Overseas buyers on the assembly floor in Dongguan, walking the line where the machines are built and run before packing.

Last updated 2026-11-20. Screw range, torque and cycle-time figures reflect the current published platform specifications.

What to specify

Key points to take away

The practical conclusions from the sections above.

Clock start

Lead time is counted from the approved drawing, not from the enquiry. Until the drawing is signed off, the build has not started.

Standard machines

7–10 days. The platform is a series we already build, so frame, motion and program are adapted rather than designed.

Custom machines

About 20 days. Fixture designed from scratch, feed proven with your screws, program written for new points.

Industry range (published, November 2026)

Standard machines quoted at 7–15 days, 10 working days, 15 days (30 in peak season) and 20–35 days by four different suppliers.

Buyer-side levers

One complete drawing, physical screw samples, numeric torque and cycle-time targets, traceability format agreed before the build.

Shipping is separate

Production time ends at packing. Transit depends on destination and mode and is quoted as its own line.

Watch the machine run

A fastening cycle on the same platform series, filmed on the assembly floor in Dongguan — the fastest way to check the motion, the feed and the torque behaviour before you ask for a drawing.

Common questions

Frequently asked questions

Does the 7–10 days include shipping?
No. It is production time up to packing. Freight is a separate leg that depends on destination and mode, and it is quoted next to the machine rather than folded into the production figure.
Can it be faster than 7 days?
Sometimes, when the platform and the fixture already exist in our build history. Ask for the date to be tied to an approved drawing in the quotation instead of accepting a range with no starting event.
When does the clock actually start?
At drawing approval. Some suppliers count from deposit instead, which is why two quotations quoting the same number of days can still mean different ship dates.
Why do some suppliers quote 15 or 30 days for a standard machine?
Usually queue depth and how much of the fixture is new. A standard platform with a fixture adapted from an existing one is a days-scale job; if the fixture is designed from scratch it is no longer a standard machine, whatever the quotation calls it.
What delays a custom machine most?
A second feed trial. If the screws do not present reliably — burrs, mixed lengths, coating — the feeder has to be reworked, and that iteration is the usual cause of a moved date.