Home / Answers / What is your lead time and minimum order quantity?
Short answerMOQ one machine. Lead time is 7–10 days for standard machines and about 20 days for custom non-standard machines — both counted from approved drawing, not from order date, which is the part buyers usually miss.
The clock starts when the drawing is approved. If the drawing discussion takes two weeks, the shipment is two weeks later, and no amount of chasing changes that.
The fastest route is to send parts and screws for a test run first; the drawing discussion is much shorter once the part has actually run on a platform.